Step 1: Apply
Complete a Residential Permit Application. This package allows you to submit one application when applying for all the required permits. There is no requirement to apply for all at one time, however to minimize wait time, we do suggest applying for all permits at once.
Step 2: Approval
Once a complete application is received, all permits will be issued within 2- 5 business days.
If a variance is required, timelines may extend up to 25 days.
Step 3: Construction
You may begin construction once you have received all required permits. Below is the contact information you may need for groundwork and utilities.
Each site is required to have an approved Fire Safety Plan posted on-site during construction.
Step 4: Inspections
All offered inspections are listed on the conditions issued with the permit.
Please see our Inspection Process page for further information on the inspection process for Single Family Dwellings.
Call 780-538-0421 or email inspections@cityofgp.com to request an inspection.