Base Building

Base Building

Permits

A lot grading, development, building and all subtrade (electrical, plumbing and gas) permits are required to construct a base building.

A base building is considered to have exterior walls with minor interior construction for future tenant development. A demising wall or mezzanine may be built as part of a base building.

Step 1: Apply

Depending on the scope of your project, you will require a variety of permits.

Please submit a complete Major Development Package.

Please submit a complete Sub Trade Application for all sub-trade permits required as per the scope of work for the project. 

Step 2: Approval

Once a complete application is received, all permits will be issued within 2- 7 business days.

In the event a variance is required for an addition, timelines may extend up to 25 days.

Step 3: Construction

You may begin construction once you have received all required permits. Below is the contact information you may need for groundwork and utilities.

Each site is required to have an approved Fire Safety Plan posted on-site during construction

Step 4: Inspections

All required inspections are listed on the conditions issued with the permit.

it is the Permit holder's responsibility to ensure all inspections are requested and received.