Permits
Cold storage is an unheated structure likely with no electricity and is not classed for human occupancy.
A development and building permit are required. Depending on the scope, an electrical permit may be required.
Step 1: Apply
Depending on the scope of your project, you will require a variety of permits.
Please submit a complete Major Development Package.
Please submit a complete Sub Trade Application if the scope of work includes electrical.
Step 2: Approval
Once a complete application is received, all permits will be issued within 2- 7 business days.
In the event a variance is required for an addition, timelines may extend up to 25 days.
Step 3: Construction
You may begin construction once you have received all required permits. Below is the contact information you may need for groundwork and utilities.
Each site is required to have an approved Fire Safety Plan posted on-site during construction
Step 4: Inspections
All required inspections are listed on the conditions issued with the permit.
it is the Permit holder's responsibility to ensure all inspections are requested and received.