City’s Road Rehabilitation Program Phase 1 Set to Begin June 3

City’s Road Rehabilitation Program Phase 1 Set to Begin June 3

This news item was published 5 years ago, and may not contain the latest information.

ARCHIVED


Article Details

Date Published:
Category: Media Releases, Roads & Transportation

The first phase of the City’s annual Road Rehabilitation program is set to begin on June 3 with construction on the following roadways:

  • 104 Avenue between 110 Street and 116 Street and 100 Avenue Services Road
    • June 3 to June 25, 2019
  • 107 Avenue between 108 Street and 110 Street
    • June 6 to June 15, 2019
  • 110 Street between 100 Avenue and 107 Avenue
    • June 18 to July 5, 2019
  • 112 Street between Highway 43 and 104 Avenue
    • June 27 to July 10, 2019

Crews will operate between 7:00 a.m. to 7:00 p.m., Monday to Saturday.

If the weather allows, the roadway upgrades are expected to be complete by mid-July. Work will include cold milling, full depth reclamation, hot mix asphalt placement, concrete work, line painting, and landscaping.

The City and contractor aim to minimize traffic delays throughout the project. It is expected that some locations will be down to one lane alternating traffic at some times.

About Road Rehabilitation

Throughout the summer, $9.7 million will be invested in the City’s road network through all phases of the annual road rehabilitation program. The investment helps prolong the life of existing roadways and replace roadways at the end of their life.