84 Avenue Bridge Repairs Begin Tomorrow

84 Avenue Bridge Repairs Begin Tomorrow

This news item was published 2 years ago, and may not contain the latest information.

Article Details

Date Published:
Category: Media Releases, Roads & Transportation

On Wednesday, June 15, the City begins repairing the eastbound and westbound bridges on 84 Avenue located between Mission Heights Drive and 100 Street.

The work includes:

  • Westbound bridge
    • deck joint cover plate repair for the curb at the northeast corner of the bridge
    • pressure-injecting epoxy into cracks in the curbs
  • Eastbound bridge
    • concrete repairs on the retaining wall and curbs
    • saw cutting asphalt above both retaining walls

During construction, traffic is reduced to a single lane while there are workers on the bridge deck and speeds will be slowed down to 30 km/h when necessary.

Pedestrian access will be maintained under the bridge. Signage will be posted to alert pedestrians as they approach the bridge of construction ahead.

Construction is expected to be completed at the end of June.

For more information on construction,  visit cityofgp.com/construction2022 or contact the City by phone at 311 or e-mail at info@cityofgp.com.