Following alternating lane closures to accommodate construction, 84 Avenue fully opens to traffic as of this afternoon (July 3) between 108 Street and Mission Heights Drive.
East of Mission Heights Drive to just before the bridge, eastbound lanes remain closed. Westbound lanes are operating with two-way traffic to maintain flow in both directions, though reduced lane access remains in place to allow for landscaping work.
Beginning Monday, July 7, eastbound lanes will close again for Full Depth Reclamation (FDR). This phase is expected to take approximately one week, weather and site conditions permitting.
For more information, view the traffic planner map at cityofgp.com/construction.
Thank you for your continued patience as construction progresses.