The City's Storm Replacement and Rehabilitation Program is an annual program for the maintenance and replacement of underground and above-ground storm infrastructure.
If you have questions regarding the Storm Replacement and Rehabilitation Program or are seeking more information, please call AcessGP at 780-538-0300 or 311 if you're within city limits.
Ditch Repairs and Culvert Replacement
Location: Township Road 721 between Range Road 71 and Range Road 70
Scope of Construction: Reconstruction of the existing ditch and culvert replacements
Proposed Completion: June 2022
Location: Range Road 53, immediately north of 132 Avenue
Scope of Construction: Replace existing CSP pipe with a concrete box culvert.
Proposed Completion: June 2022
Storm Repair and Storm Outfall Replacement
Site 1:
Location: Starting at the laneway midblock north of 109 Avenue and 105 Street heading west to near 106 Street
Scope of Construction: Replacement of damaged storm line due to it reaching the end of its life along with related storm structures
Proposed Completion: November 2022
Site 2:
Location: North of 108 Avenue from 108 Avenue to laneway north of 108 Avenue and along laneway east to 104 Street
Scope of Construction: Replacement of up to two catchbasins and of failing storm line. Potentially may involve storm line replacement due to challenging access
Proposed Completion: November 2022
Site 1:
Location: Approx 50 meters northwest of the skate park at Muskoseepi Park
Scope of Construction: Repair of a damaged storm outfall structure including installation of energy dissipation
Proposed Completion: November 2022
Site 2:
Location: West of the Bear Creek Outdoor Pool
Scope of Construction: Repair and replacement of failing storm lines and the replacement of the outfall
Proposed Completion: November 2022
Site 3:
Location: Northwest side of Heritage Village
Scope of Construction: Repair of a substantially blocked/damaged sewer line
Proposed Completion: November 2022
Site 4:
Location: Approximately 10 meters northeast of GP Museum
Scope of Construction: Replacement of failing outfall along with adjacent piping infrastructure to repair damage as a result of a sinkhole likely caused by sewer damage
Proposed Completion: November 2022
Stormwater Management Upgrades
Scope of Construction: Maintenance and safety upgrades to the Bear Creek Dam and nearby land located in Muskoseepi Park. Work includes vegetation removal, concrete repairs, trail replacements, installation of debris barrier, upgrade of retaining walls, and electrical work.
Proposed Completion: November 2022
Location: 84 Avenue west of 115 Street (Eastbound Lanes)
Scope of Construction: Sewer upgrades
Proposed Completion: October 2022
Mountview Storm
Location: Intersection of 111 Avenue and 97 Street heading 50 meters south on 97 Street and 150m east on 111 Avenue
Scope of Construction: Repair and replacement of failed pavement structure
Proposed Completion: August 2022
Location: 109 Avenue and 96A Street and into St. Clements Schoolyard
Scope of Construction: Replacement of failed asphalt and completion of landscaping work missed due to winter shutdown
Proposed Completion: August 2022
Aquatera Sanitary Sewer Twinning Project
Scope of Construction: Sanitary Sewer Replacement
Proposed Completion: October 2022
Disclaimer
Google Translate is provided as a free tool to enhance the usability of the City of Grande Prairie website. As such, the City of Grande Prairie is not responsible for Google Translate™.